Water district adopts a St. Johns River basin plan that targets Lake Jesup's phosphorus-laden sediment

The St. Johns River Water Management District board approved its Middle St. Johns River Basin Plan, which lists a $15 million sediment treatment and a proposed $22.6 million filtering plant for Lake Jesup.

Tobias Oakley· AI-assisted, edited by Jake Team

November 15, 20262 min read

Lake Restoration - illustration, Jake Team LLC

The St. Johns River Water Management District's governing board has adopted a new long-range plan for the middle stretch of the St. Johns River, and Lake Jesup, the lake off the Central Winds Park dock, sits near the top of its restoration list.

The board approved the Middle St. Johns River Basin Plan at its meeting last Tuesday, according to a district announcement posted Nov. 12. The plan sets the district's priorities for water quality, springs protection and flood protection across a basin of more than 2,000 square miles, running from the Econlockhatchee River to north of Lake George and taking in lakes Harney, Jesup, Monroe and George.

It was written with local governments, environmental groups and state agencies and went through public comment before the vote.

"This plan provides a clear path forward for protecting the Middle St. Johns River Basin's valuable water resources," said Cammie Dewey, the district's strategic planning basin coordinator, in the announcement.

Two projects aimed at the lake bottom

The draft released for comment in July describes Lake Jesup's problem as more than runoff. Decades of nutrient loading, from past wastewater discharges, urban development and farming, left nutrient-rich sediment that keeps feeding phosphorus back into the water, and the lake gets limited flushing from the river.

The draft says local projects have cut outside nutrient loads by more than the state's cleanup plan for the lake requires, but the lake's targets for nitrogen, phosphorus and chlorophyll-a still have not been met.

The draft lists two major projects for the lake:

  • Sediment treatment. A $15 million legislative appropriation received in July 2025 pays for spreading lanthanum-modified bentonite, a clay that locks up phosphorus in the sediment so algae cannot use it. The work was expected to start in the 2026-27 fiscal year and finish by summer 2031.
  • An offline treatment plant. Water would be pumped from the lake, run through nutrient-absorbing media and returned, at a 9.7-acre district property on the east shore. The district has committed about $1.39 million to a pilot test and design. The draft puts the full-scale project's preliminary construction cost at about $22.6 million and estimates it could remove about 50,000 pounds of nitrogen and 5,000 pounds of phosphorus a year.

The draft also notes that the Loch Haven chain of lakes in Winter Park and Orlando drains to Lake Jesup, and that flood and water quality projects from a district study there are now in design.

The district's announcement did not say whether the adopted plan changed any of the draft's figures. It is the third of four basin plans the board is taking up this year; the Lower St. Johns River plan comes later.

Sources

sjrwmd.com

aws.sjrwmd.com

winterspringsfl.org

Share

Tobias Oakley· AI-assisted, edited by Jake Team

Tobias Oakley writes about community life, schools, public safety, and local events in Winter Springs.

Related Stories

More in Florida