Seminole County would collect $3.65 million and bar a fired sewer contractor from its bids for 10 years under a settlement up Tuesday

The deal ends lawsuits over the Country Club Heights sewer and water main job, which the county says was about 30% done when it halted work. The termination would be recast as one for convenience.

Tobias Oakley· AI-assisted, edited by Jake Team

November 6, 20262 min read

Civic Settlement - illustration, Jake Team LLC

Seminole County commissioners will be asked Tuesday to approve a $3.65 million settlement that would close out the legal fight over a sewer and water main replacement in the Country Club Heights subdivision, a project the county took away from its contractor two years ago.

The agreement, listed on the consent agenda for the Board of County Commissioners' 9:30 a.m. meeting on Nov. 10, was reached at mediation on Oct. 12 among the county, Benchmark Construction Co. of Bartlett, Ill., and the contractor's bonding company, Liberty Mutual Insurance Co., according to the agenda item from County Attorney Kate Latorre.

Terms

Under the proposed deal:

  • Liberty Mutual would pay $3,650,000 to the county.
  • All three parties would drop their lawsuits and release any claims under the contract.
  • The county would change its 2024 termination of Benchmark from one "for cause" to one "for convenience."
  • Benchmark would not bid on or propose any county work for 10 years from the date the settlement takes effect.

Claims that Benchmark and Liberty Mutual brought against CHA, the county's design engineer, are not part of the settlement and remain pending, the agenda item says.

How the project unraveled

Commissioners awarded Benchmark the job for $3,873,725 in April 2022 after the county extended the bid deadline three times and still drew only one bid, according to earlier county agenda records. The contract allowed 540 days to reach substantial completion, later pushed to March 29, 2024, through change orders.

By June 2024, county staff reported the project was about 30% finished, that the work did not meet specifications, and that construction had caused emergencies in the neighborhood, among them sewage escaping uncontrolled and water pressure dropping, prompting a stop-work order on March 6, 2023.

The county issued a notice of breach to the surety in May 2024 and voted to terminate Benchmark for cause on Nov. 12, 2024, after its engineer and an independent consultant concluded the work did not meet contract requirements.

Liberty Mutual then sued the county and CHA, and the county countersued Benchmark and Liberty Mutual, according to the settlement summary. The agenda materials do not lay out Benchmark's account of the dispute.

The project lies in County Commission District 4.

Sources

seminolecountyfl.legistar1.com

webapi.legistar.com

webapi.legistar.com

webapi.legistar.com

Share

Tobias Oakley· AI-assisted, edited by Jake Team

Tobias Oakley writes about community life, schools, public safety, and local events in Winter Springs.

Related Stories

More in Florida