Palm Valley's plan for a new wastewater plant goes back for revisions after county review

Seminole County reviewers listed 18 unresolved questions on the Palm Valley senior community's plan to replace its wastewater treatment plant, including what exactly would be rebuilt.

Tobias Oakley

October 14, 20262 min read

Site Plan Review - illustration, Jake Team LLC

The owner of Palm Valley, a 55-and-older community in unincorporated Seminole County, wants to replace the wastewater treatment plant that serves its homes, but county reviewers say they need far more detail before they can sign off.

Hometown Palm Valley LLC, listed by the county property appraiser as owner of the 227-acre property at 3700 Palm Valley Circle (Oviedo mailing address), filed a site plan application in August. County records place the proposed plant north of Christmas Palm Place and west of Palm Valley Drive.

That acreage covers the whole parcel, homes and RV storage included; the records do not give the plant's size or treatment capacity.

The community runs its own water and sewer utility, the Palm Valley Association, and sits outside Seminole County's utility service area, according to the county's review.

Where the county review stands

A staff comment document dated Oct. 1 lists 18 items as unresolved and calls for a resubmittal. Among them:

  • Planning staff asked what exactly is being replaced, whether the entire plant or only parts of it, and asked the applicant to mark the work area on a plan of the full property.
  • Comprehensive planning staff wrote that the use "does not appear consistent" with the parcel's medium density residential land use designation.
  • Natural resources staff asked for a clearer plan showing whether any vegetated habitat would be affected, and planning staff asked for a note that the site lies in the Econ Protection Area.
  • Engineering staff said notes on the submitted plan could not be read, so the scope of work could not be determined, and the fire marshal asked for fire access and gate details.
  • Staff also asked for a current survey, noting the one provided was dated Jan. 4, 2019.

Under county code, an approved site plan can be appealed to the County Commission, which builds in a 30-day wait before work, the review notes.

Wednesday's agenda

WKMG reported that the owner would ask the county's Development Review Committee on Wednesday morning to approve the plan. The committee's final agenda for its 9 a.m. Oct. 14 session, however, placed the Palm Valley item under "comments only," which the agenda says are not discussed at the meeting.

What residents say

WKMG reported that Palm Valley dates to the early 1990s and has about 790 homes. Dale Flanagan, a resident of six years, told the station he sees the need for a new plant but worries about costs being passed on to homeowners. "I'm on a fixed income," he said.

The station noted that Winter Springs is working on its own wastewater overhaul. The city broke ground in July on the first of a pair of new treatment plants, a project approved after a 2020 breakdown at its existing plant spilled over 10,000 gallons of sewage that had been only partly treated into nearby waterways, WKMG reported.

Completion of that first plant is expected in 2028.

Sources

clickorlando.com

seminolecountyfl.legistar.com

seminolecountyfl.legistar.com

seminolecountyfl.legistar.com

seminolecountyfl.legistar.com

Share

Tobias Oakley

Tobias Oakley writes about community life, schools, public safety, and local events in Winter Springs.

Related Stories

More in Florida