Expressway board approves $12.1 million design contract for SR 417 link to Sanford airport

The 1.6-mile SR 452 Seminole Connector would tie SR 417 to Lake Mary Boulevard near Orlando Sanford International Airport, with construction targeted for 2031.

Tobias Oakley

October 9, 20262 min read

Sanford airport road design - illustration, Jake Team LLC

The Central Florida Expressway Authority board on Thursday approved a $12.1 million contract with DRMP Inc. to design State Road 452, a planned 1.6-mile expressway between SR 417 and the area around Orlando Sanford International Airport.

The road, called the Seminole Connector, would start on SR 417 close to its Lake Jesup toll plaza and end at Lake Mary Boulevard by Red Cleveland Boulevard in the Sanford area, according to CFX. Plans show a Lake Mary Boulevard interchange plus a partial SR 417 interchange whose ramps carry traffic to and from the south, the direction of Winter Springs and Oviedo.

CFX's staff presentation describes a two-lane road that could later be widened to four lanes.

What it could mean for SR 417 drivers

CFX describes the connector as another way to reach East Lake Mary Boulevard, Red Cleveland Boulevard and the airport, and says it would improve traffic flow, give emergency vehicles more reliable trip times and add evacuation options.

The design work approved Thursday also includes moving the existing Jesup mainline toll site on SR 417 farther south, below the new interchange, according to the contract scope in the board's agenda packet. The road itself does not enter Winter Springs.

Contract and timeline

DRMP ranked first among three firms, ahead of HDR Inc. and G-A-I Consultants Inc., according to the staff presentation. The approved fee is $12.1 million. Seminole County and CFX reached an interlocal agreement on the project in February, design is set to begin in November, and construction is expected to start in 2031.

CFX's fact sheet lists design wrapping up in early 2030 and notes that the schedule could change.

What officials said

Seminole County Commissioner Andria Herr, the CFX board's vice chairman, said the project has the backing of local business, local governments and the county's money. "This cannot happen fast enough," she said at the meeting, according to FOX 35. She said fast residential growth near the airport means waiting would make the road more expensive and more disruptive later.

County Manager Darren Gray described the connector as something Seminole County has sought for years. Sheryl Nichols of the Seminole County Chamber said the airport would struggle to keep expanding its industrial and manufacturing capacity without it.

No opposition to the contract was reported. Questions about the project can go to CFX's design team at 407-505-5594 or Design@CFXway.com.

Sources

cfxway.com

cfxway.com

cfxway.com

cfxway.com

fox35orlando.com